NASA completed integration of the SLS core stage with its twin solid rocket boosters inside High Bay 3 of the Vehicle Assembly Building at Kennedy Space Center on October 28, 2026. The 212-foot core stage was lifted from High Bay 2 using a custom lifting beam designed specifically to position the stage onto the mobile launcher. The result is the "short stack" configuration — core stage plus boosters — that forms the structural backbone of the Artemis III launch vehicle. The stacking sequence ran from October 22 through October 28. Technicians first lifted the core stage vertical in the transfer aisle on October 22, moved it horizontally on October 23, and completed booster integration by October 25, with final mating confirmed on October 28. The pace reflects hard-won lessons from Artemis I and II processing, where VAB integration timelines stretched far beyond plan. Next in the sequence: once testing and checkouts inside the VAB are complete, the core stage and booster stack will roll out to Launch Pad 39B for a tanking test. Liquid hydrogen and liquid oxygen will be loaded into the core stage only, while launch teams practice countdown procedures and timelines. This wet dress rehearsal is the last major ground verification before full vehicle stacking with the Orion spacecraft and upper stage. Artemis III will carry NASA astronauts Randy Bresnik, Frank Rubio, and Andre Douglas alongside ESA astronaut Luca Parmitano aboard the Orion spacecraft. The mission's primary objective is testing rendezvous and docking capabilities between Orion and commercial spacecraft from both Blue Origin and SpaceX. This is the integration demo that must succeed before any crewed lunar landing mission can proceed. The mission architecture reveals both ambition and institutional reality. NASA is routing its Moon program through not one but two commercial partners — Blue Origin's Human Landing System and SpaceX's Starship — while retaining the government-built SLS and Orion as the crew-rated trunk line. Whether this hybrid model generates genuine capability or merely distributes cost and blame across more contractors is the question Artemis III will begin to answer. The SLS remains the most expensive launch vehicle in active development, with per-launch costs that dwarf commercial alternatives. But the rocket exists, it has flown, and the workforce and infrastructure at KSC are built around it. Artemis III is less a statement about optimal rocket design and more a test of whether NASA's public-private architecture can execute a multi-vehicle, multi-partner deep-space mission. The short stack sitting in High Bay 3 is the first physical proof point.