NextDC, Australia's largest datacentre operator, wanted to double its M3 facility in west Melbourne. The physics were simple: more compute requires more electricity. The delivery mechanism was not. Electricity provider Jemena proposed replacing timber poles carrying lower voltage lines with 22-metre concrete poles capable of carrying higher voltage lines along suburban streets. Residents of West Footscray said no. The community backlash was not abstract NIMBYism. Residents raised specific concerns: the physical scale of the infrastructure (22-metre poles are roughly six storeys tall, dwarfing existing streetscapes), construction noise from the expansion itself, and the prospect of diesel backup generators running during power outages. The local council had not approved the 22-metre poles. Jemena's upgrade stalled on safety concerns, site access blocked by opposition, and the missing council approval. The market response was immediate and severe. NextDC's share price dropped from over $9 to $5.69 — a decline of more than 35% — as investors priced in the delay and the possibility that the expansion timeline would slip or the cost structure would change materially. Underground cabling or rerouting through industrial zones are both more expensive than overhead lines on suburban streets. This is the physical chokepoint that AI infrastructure hype rarely mentions. Datacentres need grid-scale power delivered to specific sites. That last-mile delivery — the actual poles and wires — runs through places where people live. The gap between announcing capacity and energizing it is not a software problem. It is a planning-permission, pole-height, neighbourhood-consent problem. NextDC and Jemena are now exploring alternatives: routing upgraded power lines through industrial zones or burying cables underground. Both options cost more and take longer. The company has not disclosed revised timelines or cost estimates for the M3 expansion. The West Footscray standoff is a microcosm of a pattern playing out globally. AI datacentre demand is growing faster than grid infrastructure can adapt, and the constraint is not generation capacity alone — it is the physical delivery network. Every proposed expansion must thread through existing urban fabric, and communities are increasingly willing to fight back when the costs land on their streets. The Guardian's visual explainer notes the poles' scale in relatable terms: taller than a brachiosaurus, roughly equivalent to a six-storey apartment building. The comparison lands because it makes the abstraction visceral. These are not minor street furniture upgrades. They are industrial-scale infrastructure being threaded through residential neighbourhoods to serve a single private facility.